DOT Update for East Hartford

November 23, 2021

The Connecticut Department of Transportation announced the permanent closures of both the Route 2 Eastbound Sutton Avenue Off-Ramp (Exit 5B) and Route 2 Westbound Cambridge Drive On-Ramp (Exit 5B).  As part of the safety and operational improvements on Route 2, the permanent ramp closures are necessary. 
 

Improvements associated with the closures include extending the acceleration and deceleration lanes in vicinity of the ramp closures, providing intersection improvements on Main Street at the Main St. off-ramp (Exit 5A) intersection, and improvements at the intersection with Main St. at Maple Street/Broad Street. 

 The following ramps will be permanently closed starting December 2, 2021, weather permitting. Temporary signage will be posted alerting the public of the closure.

  • Route 2 Eastbound Sutton Avenue Off-Ramp (Exit 5B)
  • Route 2 Westbound Cambridge Drive On-Ramp (Exit 5B)

 
Alternate routes are as follows:
 
Traffic entering Route 2 Westbound via the Cambridge Drive On-Ramp can use the following alternate on-ramps:

  • Maple Street Route 2 WB On-Ramp (0.4 miles South of Cambridge Drive)
  • Sutton Avenue to Main Street South to Maple Street
  • High Street Route 2 WB On-Ramp (0.6 miles north of Cambridge Drive)
  • Sutton Avenue to Main Street North to Brewer Street to West Brewer Street

 
Traffic exiting Route 2 Eastbound via the Sutton Avenue Off-Ramp may use the following alternate off-ramps:

  • Exit 5C Maple Street EB Off-Ramp (0.4 miles South of Sutton Ave)
  • Maple Street to Main Street to Sutton Ave
  • Exit 5A High Street EB Off-Ramp (0.6 miles North of Sutton Ave)
  • High Street to Carter Street to Main Street to Sutton Ave

 
A map of these ramp closures and associated alternate routes follows.  Motorists should exercise caution and allow additional time for their trip as this closure is implemented. Visit the DOT website for more information.